The Code Cage - Microsoft Office help Free Microsoft Office Help for all Applications!  

To stop seeing these ads and get other benefits check This page!

Go Back   The Code Cage Forums > Members - Microsoft Topics > Members - Project Forum > Members - Project Formatting
  Chat In Use Now! Microsoft Office Chat Online now!


Members - Project Formatting Members, post questions in this forum if they are related to using Microsoft Project Gantt Charts & Timelines etc.
If you recieve no reply within 1 day your thread will be reposted in the newsgroups with a redirect here.

Hey there!

It looks like you're enjoying but haven't created an account yet. Why not take a minute to register for your own free account now? As a member you get free access to all of our forums and posts plus the ability to post your own messages, communicate directly with other members and much more. Register now!

Already a member? Login at the top of this page to stop seeing this message.


Reply
 
LinkBack Thread Tools Display Modes
  #1 (permalink)  
Old 20th January 2010, 10:47 PM
Junior Member
MS Office Version: MS Office 2007
MS Office Skill Level: Proficient with MSO 2007


My Top Tip Count: 0

 
Join Date: Jan 2010
Location: Wisconsin
Posts: 4
Thanks to others: 1
Thanked 0 Times in 0 Posts
Chats: 0
Rep Power: 0
parker is on a distinguished road
USA
Default Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


I am using MS Project 2007 SP2 MSO. I have created a project and performed all the steps to create my earned value report. When I create the earned value visual report the data is transferred to Excel 2007 SP2 MSO in the form of a chart and pivot table. The pivot table shows Earned Value, Planned Value, and AC. The AC column is all zero's where the other columns contain correct data. The ACWP column in project shows the correct values.

Somehow the AC, ACWP data in project is not being transfered to excel for some reason. I have done Earned Value graphs in the past and never had this problem. Obviously I'm doing something wrong but just can seem to find the setting I'm missing.

I attached the file if it helps at all.

If someone could point me in a direction I would greatly appreciate it.
Parker

Some background of what I have done and made sure was correct.
-Baseline is set from the start of the project with the current day at the start of the project.
-I moved current date to today when creating the chart.
- I set the status date to a week after my last work entry to make sure I have all the data.
-I have resources for each task, none for summary tasks, and each resource has a $ amount to it.
-Use task usage view to enter actual hours for each resource.
-ACWP and Actual Cost are the same.
-tools/options/earned value = %complete and correct baseline.
Attached Files
File Type: zip Parker EVA.zip (99.4 KB, 2 views)

Last edited by parker; 20th January 2010 at 10:52 PM.
Reply With Quote


Did you find this post helpful? Yes | No

The Code Cage Advertisment
Advertisement

To stop seeing these ads and get other benefits check This page!
  #2 (permalink)  
Old 21st January 2010, 06:27 AM
Simon Lloyd's Avatar
Administrator
MS Office Version: MS Office 97, 2003, 2007
MS Office Skill Level: Can use most of MS Office


My Top Tip Count: 5

 
Join Date: Aug 2008
Location: Manchester, England
Age: 45
Posts: 1,924
Thanks to others: 3
Thanked 74 Times in 73 Posts
Chats: 656
Rep Power: 10
Simon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud of
5 Top Tips
Wales
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


Hi i wil take a look at this when i get home as i don't have project here, will post back later
__________________
Regards,
Simon Lloyd
Excel Chat
Reply With Quote


1 out of 1 members found this post helpful. Did you find this post helpful? Yes | No
  #3 (permalink)  
Old 22nd January 2010, 09:32 PM
Junior Member
MS Office Version: MS Office 2007
MS Office Skill Level: Proficient with MSO 2007


My Top Tip Count: 0

 
Join Date: Jan 2010
Location: Wisconsin
Posts: 4
Thanks to others: 1
Thanked 0 Times in 0 Posts
Chats: 0
Rep Power: 0
parker is on a distinguished road
USA
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


Simon,
I have tried to get the AC values to transfer to excel through the Earned Value over time visual report. I opened it today and the AC values transferred to excel and the report looked good. I added hours for today to some project tasks under task usage view. I created the report again and no AC values transferred. AC was all zero in the pivot table.

I closed down project and reopened it and the chart worked fine?

I'm starting to lean towards a project feature/bug in the calculations portion.
You can see this in my project that I attached at the start of the thread, but I attached my tools/options/calculations settings.

I am eager to find out what you think,
Thanks,
Parker
Attached Images
File Type: jpg msop2007 settings.jpg (73.4 KB, 6 views)
Reply With Quote


Did you find this post helpful? Yes | No
The Code Cage Advertisment
Advertisement

To stop seeing these ads and get other benefits check This page!
  #4 (permalink)  
Old 25th January 2010, 07:58 PM
Simon Lloyd's Avatar
Administrator
MS Office Version: MS Office 97, 2003, 2007
MS Office Skill Level: Can use most of MS Office


My Top Tip Count: 5

 
Join Date: Aug 2008
Location: Manchester, England
Age: 45
Posts: 1,924
Thanks to others: 3
Thanked 74 Times in 73 Posts
Chats: 656
Rep Power: 10
Simon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud of
5 Top Tips
Wales
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


Sorry for the delay on this parker, i will be taking a look at this tonight after i've eaten
__________________
Regards,
Simon Lloyd
Excel Chat
Reply With Quote


Did you find this post helpful? Yes | No
  #5 (permalink)  
Old 27th January 2010, 12:35 PM
Simon Lloyd's Avatar
Administrator
MS Office Version: MS Office 97, 2003, 2007
MS Office Skill Level: Can use most of MS Office


My Top Tip Count: 5

 
Join Date: Aug 2008
Location: Manchester, England
Age: 45
Posts: 1,924
Thanks to others: 3
Thanked 74 Times in 73 Posts
Chats: 656
Rep Power: 10
Simon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud of
5 Top Tips
Wales
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


What are the steps you are taking to copy to Excel?, i don't see a problem with your report.
__________________
Regards,
Simon Lloyd
Excel Chat
Reply With Quote


Did you find this post helpful? Yes | No
  #6 (permalink)  
Old 27th January 2010, 02:25 PM
Junior Member
MS Office Version: MS Office 2007
MS Office Skill Level: Proficient with MSO 2007


My Top Tip Count: 0

 
Join Date: Jan 2010
Location: Wisconsin
Posts: 4
Thanks to others: 1
Thanked 0 Times in 0 Posts
Chats: 0
Rep Power: 0
parker is on a distinguished road
USA
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


Simon,
I use Report/Visual Reports/All/Earned Value Over Time Report.
This automatically creates a pivot table and graph in excel.
That is where my problems come in. The AC values in the pivot table and graph are zero.

If you add some hours and then do the report, do you get all zeros for AC?
Parker

Quote from 1/22*************
I have tried to get the AC values to transfer to excel through the Earned Value over time visual report. I opened it today and the AC values transferred to excel and the report looked good. I added hours for today to some project tasks under task usage view. I created the report again and no AC values transferred. AC was all zero in the pivot table.

I closed down project and reopened it and the chart worked fine?

I'm starting to lean towards a project feature/bug in the calculations portion.
You can see this in my project that I attached at the start of the thread, but I attached my tools/options/calculations settings
End Quote 1/22************
Reply With Quote


Did you find this post helpful? Yes | No
The Code Cage Advertisment
Advertisement

To stop seeing these ads and get other benefits check This page!
  #7 (permalink)  
Old 27th January 2010, 03:10 PM
Simon Lloyd's Avatar
Administrator
MS Office Version: MS Office 97, 2003, 2007
MS Office Skill Level: Can use most of MS Office


My Top Tip Count: 5

 
Join Date: Aug 2008
Location: Manchester, England
Age: 45
Posts: 1,924
Thanks to others: 3
Thanked 74 Times in 73 Posts
Chats: 656
Rep Power: 10
Simon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud of
5 Top Tips
Wales
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


I need to install excel 2003 or 2007 to view that, i'm trialing a excel 2010 beta and its not picking up automatically - will post back tomorrow after i've installed it
__________________
Regards,
Simon Lloyd
Excel Chat
Reply With Quote


Did you find this post helpful? Yes | No
  #8 (permalink)  
Old 29th January 2010, 04:29 PM
Simon Lloyd's Avatar
Administrator
MS Office Version: MS Office 97, 2003, 2007
MS Office Skill Level: Can use most of MS Office


My Top Tip Count: 5

 
Join Date: Aug 2008
Location: Manchester, England
Age: 45
Posts: 1,924
Thanks to others: 3
Thanked 74 Times in 73 Posts
Chats: 656
Rep Power: 10
Simon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud of
5 Top Tips
Wales
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


Here's what i got when viewing your report:


Attached Images
File Type: jpg parker report to excel.jpg (20.4 KB, 9 views)
File Type: jpg parker chart to excel.jpg (17.0 KB, 7 views)
__________________
Regards,
Simon Lloyd
Excel Chat
Reply With Quote


1 out of 1 members found this post helpful. Did you find this post helpful? Yes | No
The Following User Says Thank You to Simon Lloyd For This Useful Post:
parker (24th February 2010)
  #9 (permalink)  
Old 24th February 2010, 09:47 PM
Junior Member
MS Office Version: MS Office 2007
MS Office Skill Level: Proficient with MSO 2007


My Top Tip Count: 0

 
Join Date: Jan 2010
Location: Wisconsin
Posts: 4
Thanks to others: 1
Thanked 0 Times in 0 Posts
Chats: 0
Rep Power: 0
parker is on a distinguished road
USA
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


Thanks Simon,
It turns out that I have to close the project and then open it before the graph will come out like yours. If I make any changes to the project, like addint actual hours to a task, the AC values will be zero. It seems like it is just a calculation error by MSProject.
Thanks for your help.
Parker
Reply With Quote


Did you find this post helpful? Yes | No
The Code Cage Advertisment
Advertisement

To stop seeing these ads and get other benefits check This page!
  #10 (permalink)  
Old 24th February 2010, 10:31 PM
Simon Lloyd's Avatar
Administrator
MS Office Version: MS Office 97, 2003, 2007
MS Office Skill Level: Can use most of MS Office


My Top Tip Count: 5

 
Join Date: Aug 2008
Location: Manchester, England
Age: 45
Posts: 1,924
Thanks to others: 3
Thanked 74 Times in 73 Posts
Chats: 656
Rep Power: 10
Simon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud ofSimon Lloyd has much to be proud of
5 Top Tips
Wales
Default Re: Earned Value Over Time Report - AC values are all zero

------ Register to get rid of these "In Post" ads! ------


That is odd, im using 2010 and it worked each time.
__________________
Regards,
Simon Lloyd
Excel Chat
Reply With Quote


Did you find this post helpful? Yes | No
The Code Cage Advertisment
Advertisement

To stop seeing these ads and get other benefits check This page!
Reply

Bookmarks

Tags
earned, report, time, values


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Forum Jump

The Code Cage Affilliates


To stop seeing these ads and get other benefits check This page!



All times are GMT +1. The time now is 12:24 PM.


Powered by vBulletin® Version 3.8.5
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.
SEO by vBSEO 3.3.2
No part of this board may be copied or reproduced either in part or full without the express permission of The Code Cage Team.
We are not associated with nor employed by Microsoft in any way, we simply provide resources!
All MS office icons are registered trademarks of the application the represent